Hastings Point Wastewater Treatment Plant performance upgrade
February 2025 update:
At Council’s meeting on 20 February 2025, it was resolved to undertake additional engineering assessment works for Option 4: constructing a third extended aeration tank (EAT) and Option 5: converting to a membrane bioreactor (MBR) process with the addition of a contact tank. The additional works are now underway and will focus on:
- further developing performance upgrade Options 4 and 5, to provide more accurate costings and consider outcomes of the noise and odour studies
- further investigating the current and future loadings on the Hastings WWTP including the impact of holiday loading
- considering all relevant legislative and regulatory requirements following the performance upgrade of the plant
- considering Options 4 and 5 in the upcoming budget.
For the full Council meeting minutes, visit Council Meeting – 20 February 2025.
It is estimated this additional work will take 12 months to complete. The additional engineering investigation report will then be provided to Council to determine a preferred option. This report will be made available on this page prior to Council decision.
The Hastings Point Wastewater Treatment Plant currently services about 12,860 people who live, work and holiday in Cabarita Beach, Bogangar, Hastings Point and Pottsville.
Ageing assets and population growth is putting pressure on the plant’s performance. While the plant is licensed by the NSW Environmental Protection Authority (EPA) to service about 18,000 people, it needs some improvement works now to ensure it can meet this licensed capacity into the future.
Community benefits
By upgrading the performance of the plant, we will be able to provide resilient and efficient wastewater services for current and future populations. The quality of treated wastewater will be higher, ensuring the plant continues to meet the conditions of its EPA licence.
Options for upgrading
In 2024, Council engaged external engineering consultants, GHD, to evaluate 5 potential upgrade options for the Hastings Point WWTP. This assessment considered technical performance, environmental impact and financial feasibility to identify the most suitable upgrade.
The consultants recommended Option 4: Construct a third extended aeration tank (EAT) as the preferred solution due to its balance of performance, cost and environmental outcomes.
The consultant's report was then subjected to a peer review by Hunter BECA, an independent engineering consultant, who also concluded that Option 4 was suitable compared to the alternatives.
Please download the draft Hastings Point Wastewater Treatment Plant Options Assessment for details on the options.
Option 4 involves:
- constructing a third extended aeration tank
- new inlet works and odour treatment system
- a 99kW solar array
- other complementary improvements
- renewal of existing components at the plant.
The GHD assessment names these benefits of Option 4:
- maintains the current plant’s operational philosophy with a familiar technology whilst increasing treatment capacity, reliability and redundancy
- relatively low technical risk in construction and commissioning
- relatively low energy consumption
- low maintenance
- reuses a large amount of existing infrastructure that has remaining life.
Have your say
In May and June 2024, Council sought community feedback on the draft Hastings Point Wastewater Treatment Plant Options Assessment. Of the submissions received:
- 50% supported the proposed performance upgrade, with some specific issues raised
- 33% were neither for nor against, with some specific issues raised
- 17% were against the proposal.
Following additional community input in late 2024 and early 2025, Council resolved to further develop both Options 4 and 5, to provide more accurate costings and to consider the outcomes of the noise and odour studies.
What’s next?
We are proceeding with additional assessment works for Options 4 and 5. It is estimated this additional work will take 12 months to complete. The additional engineering investigation report will then be provided to Council to determine a preferred option. This report will be made available on this page prior to Council decision.
Once Council has determined a preferred option, we will finalise the concept design, review environmental factors and determine planning and other government agency approvals. This is expected to take 12 months.
When these actions are complete and approvals are in place, the project will move to the detailed design stage and after that, construction will commence. This is expected to take an additional 2 years.